VersionRelease dateScopePI input deadline
38.0 04 Aug 2017 Template for Dec 2017 to May 2018    
37.3 21 Jul 2017 Plan PP896 to 904 (orbits 2714 - 2741, 30 Sep to 03 Dec) - Review deadline 18 Jul 11 Jul 2017
37.2 28 Apr 2017 Plan PP885 to 895 (orbits 2680 - 2713, 15 Jul to 30 Sep) - Review deadline 25 Apr13 Apr 2017
37.1 24 Feb 2017 Plan PP874 to 884 (orbits 2646 - 2679, 29 Apr to 15 Jul) - Review deadline 21 Feb16 Feb 2017
37.0 07 Feb 2017 Template for May 2017 to Nov 2017    
36.2 02 Dec 2016 Plan PP865 to 873 (orbits 2612 - 2645, 11 Feb to 29 Apr) - Review deadline 30 Nov 21 Nov 2016
36.1 23 Sep 2016 Plan PP855 to 864 (orbits 2581 - 2611, 03 Dec to 11 Feb) - Review deadline 21 Sep 12 Sep 2016
36.0 05 Aug 2016 Template for Nov 2016 to May 2017    
35.3 29 Jul 2016 Plan PP847 to 854 (orbits 2556 - 2580, 08 Oct to 03 Dec) - Review deadline 26 Jul 19 Jul 2016
35.2 27 May 2016 Plan PP839 to 846 (orbits 2528 - 2555, 05 Aug to 08 Oct) - Review deadline 24 May17 May 2016
35.1 01 Apr 2016 Plan PP830 to 838 (orbits 2500 - 2527, 03 Jun to 05 Aug) - Review deadline 30 Mar22 Mar
35.0 05 Feb 2016 Template for May 2016 to Nov 2016    

Notes

  • Release dates for a full MSP segment (e.g. 34.1, 34.2, etc) are before the nominal dates on which JSOC starts production of the OBRQ-lite for the first planning period in that segment.
  • Science inputs for any MSP segment should be sent to JSOC before the PI input deadline date.
  • Any tbd values in the final record will be firmed up when the preceding template is generated.